East Street to Reopen Under Traffic Control

On Display Indefinitely

Council wishes to advise that East Street will be open to traffic from Thursday 28 March 2024, with ongoing works planned to finalise the project to be carried out under traffic control.

The following works will be completed by Tuesday 30 April 2024:

  • Guardrail installation
  • Channel widening and rock armouring
  • Footpath, kerbing and verge shaping

The following works to finalise the project will be completed by Friday 31 May 2024:

  • Asphalt resurfacing in rail corridor
  • Carpark shaping and sealing
  • Line marking

In order to ensure your safety and the safety of those working on the project, Council asks that you please adhere to traffic control measures.

We appreciate your understanding and cooperation as we work towards finalising this project.