Council wishes to advise that upgrades to the stormwater network currently being undertaken along Reid Street, between Renshaw McGirr Way and East Street, are progressing well however due to some inclement weather and unsuitable ground conditions, the project has experienced some minor delays.
The completion date for the project has been extended from Friday 25 August 2023 to Friday 15 September 2023, weather permitting.
As Council have encountered rock during excavation works, intermittent use of a rock hammer will be required which will be limited to the hours of 8:30am to 3:00pm daily, to minimise disruption.
The works continue to be completed under a road closure during the day between 7:00am and 5:00pm and re-opened outside these hours with changed traffic conditions. Residents and businesses are requested to exercise caution at all times when around the work area and to follow the instructions of Traffic Control staff on site.
Should you have any queries in relation to these works, please contact Council's Executive Manager Operations, Mr Logan Hignett, on 6861 2343.