PAC Park Flood Damage Repair

  • Project value$701,545
  • Project scheduleConstruction underway
Picture1.png

Repairs to flood damage at PAC Park will include stabilisation of the creek banks, replacement of two pedestrian footbridges and a damaged footpath. These works will ensure the park is safe for public use and that connecting infrastructure remains accessible.

Scope of work:

Activity 1

  • Detailed designs completed, contractors engaged, and materials procured.
  • Site investigations and surveys completed.
  • Site established, including sedimentation and erosion controls, and relocation of  Telstra and water services.
  • Bank stabilisation commenced with stone pitching, ground shaping and vegetation planting (approx. 100m).

Activity 2

  • Demolition and removal of two existing 15m pedestrian bridges.

Activity 3 / Project Completion

  • Delivery and installation of two new 15m prefabricated pedestrian bridges.
  • Construction of a 150m concrete footpath linking to the Newell Highway pathway.
  • Final ground works, including turfing, topsoiling and irrigation.
  • Completion of bridge footings and bank stabilisation works.

Project updates

April 2026 update

PAC Park has now reopened to the community following the completion of creek clearing works.

Current works are focused on stabilising creek banks, improving drainage, and upgrading key infrastructure to enhance safety, accessibility, and resilience during future weather events.

While the park is now open for public use, bridge sites will remain securely fenced as work continues, including the removal and replacement of two pedestrian bridges.

Picture1.jpg

June 2026 update

The project continues to progress, with creek clearing and rehabilitation works now complete.

The bridge design has been updated in response to Council's review, with final design work continuing ahead of fabrication. Expenditure is currently tracking at approximately 17% of the overall project budget, in line with the revised project program.

Upcoming works include the removal of cleared spoil from the site, finalisation of the bridge design, and commencement of bridge fabrication in accordance with the revised project schedule.

Further activities will focus on revegetation, including planting trees along the creek banks, and preparing the site for installation of the new bridges.

 