The project continues to progress, with creek clearing and rehabilitation works now complete.
The bridge design has been updated in response to Council's review, with final design work continuing ahead of fabrication. Expenditure is currently tracking at approximately 17% of the overall project budget, in line with the revised project program.
Upcoming works include the removal of cleared spoil from the site, finalisation of the bridge design, and commencement of bridge fabrication in accordance with the revised project schedule.
Further activities will focus on revegetation, including planting trees along the creek banks, and preparing the site for installation of the new bridges.